Which of the following is the activity that compares the planned test progress to the actual test progress?
選択肢
正解
A: Test monitoring
解説
A is correct. Test monitoring involves the on-going comparison of actual progress against the test plan. B is incorrect because it defines testing objectives. C is incorrect because the activities have already completed and the project is closing down. D is incorrect because test control is when you take actions to correct any issues observed during monitoring.