Which of the following is the activity that compares the planned test progress to the actual test progress?

Answer Options

A.Test monitoringโœ“
B.Test planning
C.Test closure
D.Test control

Correct Answer

A: Test monitoring

Explanation

A is correct. Test monitoring involves the on-going comparison of actual progress against the test plan. B is incorrect because it defines testing objectives. C is incorrect because the activities have already completed and the project is closing down. D is incorrect because test control is when you take actions to correct any issues observed during monitoring.