Which of the following is the activity that compares the planned test progress to the actual test progress?

Các đáp án

A.Test monitoring
B.Test planning
C.Test closure
D.Test control

Đáp án đúng

A: Test monitoring

Giải thích

A is correct. Test monitoring involves the on-going comparison of actual progress against the test plan. B is incorrect because it defines testing objectives. C is incorrect because the activities have already completed and the project is closing down. D is incorrect because test control is when you take actions to correct any issues observed during monitoring.