When following a standard test process, when should the test control activity take place?

Các đáp án

A.During the planning activities
B.During the implementation and execution activities
C.During the monitoring activities
D.During all the activities

Đáp án đúng

D: During all the activities

Giải thích

D is correct. Control occurs throughout the project to ensure that it is staying on track based on the plan and to take any corrective steps that may be necessary. The monitoring information is used to determine if control actions are needed.

Câu hỏi khác trong đề thi này