Which of the following is the activity that compares the planned test progress to the actual test progress?

Opções de Resposta

A.Test monitoring
B.Test planning
C.Test closure
D.Test control

Resposta Correta

A: Test monitoring

Explicação

A is correct. Test monitoring involves the on-going comparison of actual progress against the test plan. B is incorrect because it defines testing objectives. C is incorrect because the activities have already completed and the project is closing down. D is incorrect because test control is when you take actions to correct any issues observed during monitoring.