When the tester verifies the test basis while designing tests early in the lifecycle, which test objective is being achieved?
選択肢
正解
C: Evaluating work products
解説
C is correct per the syllabus. The other three are achieved primarily by doing dynamic testing. This is a bit tricky because you are very likely to find defects while doing this analysis and this may lead to either gaining or destroying confidence and needing to supply information to the decision makers. What is occurring here is an evaluation of the work product, in this case the requirements.