Câu 75Foundation 2018 Sample Exam 1

Which of the following is an example of a good exit criterion from system testing?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Các đáp án

A.All tests should be completed
B.The project budget should be spent
C.All defects should be fixed
D.All severity 1 defects must be resolved✓

Đáp án đúng

D: All severity 1 defects must be resolved

Luyện thi bộ đề nàyXem tất cả câu hỏi

Câu hỏi khác trong đề thi này

#40

What is the test basis?

#41

When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?

#42

When following the fundamental test process, when should the test control activity take place?

#43

Which of the following is a correct statement?

#44

Which of the following is an example of debugging?