Which of the following is an example of a good exit criterion from system testing?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Các đáp án

A.All tests should be completed
B.The project budget should be spent
C.All defects should be fixed
D.All severity 1 defects must be resolved

Đáp án đúng

D: All severity 1 defects must be resolved