Questão 75Foundation 2018 Sample Exam 1

Which of the following is an example of a good exit criterion from system testing?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Opções de Resposta

A.All tests should be completed
B.The project budget should be spent
C.All defects should be fixed
D.All severity 1 defects must be resolved✓

Resposta Correta

D: All severity 1 defects must be resolved

Praticar Este ConjuntoVer Todas as Questões

Mais Questões desta Prova

#40

What is the test basis?

#41

When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?

#42

When following the fundamental test process, when should the test control activity take place?

#43

Which of the following is a correct statement?

#44

Which of the following is an example of debugging?