ISTQB Quiz
nav.blog試験セット問題練習クイズ
ENVIDEPTJA
ENVIDEPTJA

ISTQB Quiz

ISTQB Foundation Level 無料練習テスト

(c) 2026 ISTQB Quiz - Not affiliated with ISTQB

ホーム/問題/#75
問題 75Foundation 2018 Sample Exam 1

Which of the following is an example of a good exit criterion from system testing?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

選択肢

A.All tests should be completed
B.The project budget should be spent
C.All defects should be fixed
D.All severity 1 defects must be resolved✓

正解

D: All severity 1 defects must be resolved

この試験セットで練習するすべての問題を見る

この試験の他の問題

#40

What is the test basis?

#41

When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?

#42

When following the fundamental test process, when should the test control activity take place?

#43

Which of the following is a correct statement?

#44

Which of the following is an example of debugging?