What is the primary reason to get early and frequent feedback from stakeholders regarding a product being developed?

Các đáp án

A.To make them feel involved
B.To ensure that their vision for the product will be realized
C.To create more meetings
D.To use the stakeholders as testers

Đáp án đúng

B: To ensure that their vision for the product will be realized

Giải thích

B is correct per the syllabus. By getting their feedback, the team can ensure that what they are building is what the stakeholders want. A is not correct because, although it may be beneficial to have them feel a part of the team, it isn’t the primary reason to get their feedback. C is not correct because no one needs more meetings. D is not correct although stakeholders may be used for UAT. Their feedback is needed much earlier than UAT.