What is the primary reason to get early and frequent feedback from stakeholders regarding a product being developed?

Answer Options

A.To make them feel involved
B.To ensure that their vision for the product will be realized✓
C.To create more meetings
D.To use the stakeholders as testers

Correct Answer

B: To ensure that their vision for the product will be realized

Explanation

B is correct per the syllabus. By getting their feedback, the team can ensure that what they are building is what the stakeholders want. A is not correct because, although it may be beneficial to have them feel a part of the team, it isn’t the primary reason to get their feedback. C is not correct because no one needs more meetings. D is not correct although stakeholders may be used for UAT. Their feedback is needed much earlier than UAT.