The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case: ï‚· Best-case scenario: 1 hour ï‚· Worst-case scenario: 8 hours ï‚· Most likely scenario: 3 hours Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases?

Req1Req2Req3Req4Req5Req6Req7
TC1XXXX
TC2XXX
TC3XX
TC4X

Answer Options

A.14 hours✓
B.3.5 hours
C.16 hours
D.12 hours

Correct Answer

A: 14 hours