The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case:  Best-case scenario: 1 hour  Worst-case scenario: 8 hours  Most likely scenario: 3 hours Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases?

Req1Req2Req3Req4Req5Req6Req7
TC1XXXX
TC2XXX
TC3XX
TC4X

Antwortmöglichkeiten

A.14 hours
B.3.5 hours
C.16 hours
D.12 hours

Richtige Antwort

A: 14 hours