Question 375ISTQB CTFL v4.0 Sample Exam C
At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation: 3 β π΄(π β 1) + π΄(π β 2) πΈ(π) = 4 The graph shows the estimated and actual amount of work for the first four iterations. Estimated and actual effort (in person-days) 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Iteration #1 Iteration #2 Iteration #3 Iteration #4 Estimated Actual What is the estimated amount of work for iteration #5?
Answer Options
A.10.5 person-days
B.8.25 person-days
C.6.5 person-daysβ
D.9.4 person-days
Correct Answer
C: 6.5 person-days