Given the following testware: 1. Coverage items 2. Change requests 3. Test execution schedule 4. Prioritized test conditions And the following test activities

Answer Options

A.1B, 2D, 3C, 4A✓
B.1B, 2D, 3A, 4C
C.1D, 2C, 3A, 4B
D.1D, 2C, 3B, 4A

Correct Answer

A: 1B, 2D, 3C, 4A