Given the following testware: 1. Coverage items 2. Change requests 3. Test execution schedule 4. Prioritized test conditions And the following test activities

Các đáp án

A.1B, 2D, 3C, 4A
B.1B, 2D, 3A, 4C
C.1D, 2C, 3A, 4B
D.1D, 2C, 3B, 4A

Đáp án đúng

A: 1B, 2D, 3C, 4A

Câu hỏi khác trong đề thi này