Which of the following is a project risk?

Answer Options

A.A defect that is causing a performance issue
B.A duplicate requirement
C.An issue with a data conversion procedure
D.A schedule that requires work during Christmas shutdownโœ“

Correct Answer

D: A schedule that requires work during Christmas shutdown