Question 111Foundation 2018 Sample Exam 2
Which of the following is a project risk?
Answer Options
A.A defect that is causing a performance issue
B.A duplicate requirement
C.An issue with a data conversion procedure
D.A schedule that requires work during Christmas shutdownโ
Correct Answer
D: A schedule that requires work during Christmas shutdown