Which of the following is a project risk?

Antwortmöglichkeiten

A.A defect that is causing a performance issue
B.A duplicate requirement
C.An issue with a data conversion procedure
D.A schedule that requires work during Christmas shutdown

Richtige Antwort

D: A schedule that requires work during Christmas shutdown