You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7. The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority). The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed. Which test case should be executed sixth?
Các đáp án
A.TC 3✓
B.TC 5
C.TC 6
D.TC 2
Đáp án đúng
A: TC 3