During a period of intensive project overtime, a system architecture document is sent to various project participants, announcing a previously-unplanned technical review to occur in one week. No adjustments are made to the participants’ list of assigned tasks. Based on this information alone, which of the following is a factor for review success that is MISSING?
選択肢
正解
B: Adequate time to prepare