During a period of intensive project overtime, a system architecture document is sent to various project participants, announcing a previously-unplanned technical review to occur in one week. No adjustments are made to the participants’ list of assigned tasks. Based on this information alone, which of the following is a factor for review success that is MISSING?

Antwortmöglichkeiten

A.Appropriate review type
B.Adequate time to prepare
C.Sufficient metrics to evaluate the author
D.Well-managed review meeting

Richtige Antwort

B: Adequate time to prepare