Which of the following BEST define EXIT criteria in a testing project?

Req1Req2Req3Req4Req5Req6Req7
TC1XXXX
TC2XXX
TC3XX
TC4X

Answer Options

A.The budget is approved
B.Budget runs out✓
C.Test basis is available
D.Test cases achieved at least 80% statement coverage✓
E.All test analysts are ISTQB certified at the Foundation Level

Correct Answer

B, D: Budget runs out; Test cases achieved at least 80% statement coverage