During which level(s) of testing should non-functional tests be executed?

Answer Options

A.Unit and integration only
B.System testing only
C.Integration, system and acceptance only
D.Unit, integration, system and acceptance onlyโœ“

Correct Answer

D: Unit, integration, system and acceptance only

Explanation

D is correct. Non-functional tests can and should be executed at all levels of testing.