Who is normally responsible for the creation and update of a test plan for a project?
Các đáp án
A.The project manager
B.The test manager✓
C.The tester
D.The product owner
Đáp án đúng
B: The test manager
Các đáp án
Đáp án đúng
B: The test manager
What is the test basis?
#41When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?
#42When following the fundamental test process, when should the test control activity take place?
#43Which of the following is a correct statement?
#44Which of the following is an example of debugging?