During a risk analysis the following risk was identified and assessed: Risk: Response time is too long to generate a report Risk likelihood: medium; risk impact: high Response to risk: o an independent test team performs performance testing during system testing o a selected sample of end users performs alpha and beta acceptance testing before the release What measure is proposed to be taken in response to this analyzed risk?
Các đáp án
Đáp án đúng
C: Risk mitigation