Questão 74Foundation 2018 Sample Exam 1

You are working in a team of testers who are all writing test cases. You have noticed that there is a significant inconsistency with the length and amount of detail in the different test cases. Where should the test case guidelines have been documented?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Opções de Resposta

A.The test plan✓
B.The test approach
C.The test case template
D.The project plan

Resposta Correta

A: The test plan

Praticar Este ConjuntoVer Todas as Questões

Mais Questões desta Prova

#40

What is the test basis?

#41

When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?

#42

When following the fundamental test process, when should the test control activity take place?

#43

Which of the following is a correct statement?

#44

Which of the following is an example of debugging?