Questão 35CTFL 4.0 Sample Exam3 2

Your team is using Planning Poker to estimate the effort for a story. Developer Vote Tester Vote First vote 3 8 Second vote 5 8 Third vote 5 5 Although three votes were taken to reach consensus, how many story points should be allocated to the story?

Developer VoteTester Vote
First vote38
Second vote58
Third vote55
Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Opções de Resposta

A.10 because that’s the sum of the points
B.8 because that was the highest number
C.3 because that was the lowest number
D.5 because that was the consensus✓

Resposta Correta

D: 5 because that was the consensus

Explicação

D is correct. Voting should continue until consensus is reached and that number should be used to assign the points to the story.

Praticar Este ConjuntoVer Todas as Questões

Mais Questões desta Prova

#1

When the tester verifies the test basis while designing tests early in the lifecycle, which test objective is being achieved?

#2

In some Agile teams, people are encouraged to use their skills to help the team, regardless of their role. This could mean that testers help the developers write code and developers help testers test. What is this approach called?

#3

Which of the following is a correct statement?

#4

Why is it important to avoid the principle of tests wearing out?

#5

When following a standard test process, when should the test control activity take place?