Questão 34CTFL 4.0 Sample Exam3 2

If the developers are releasing code for testing that is not version controlled, what process is missing?

Developer VoteTester Vote
First vote38
Second vote58
Third vote55
Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

Opções de Resposta

A.Configuration management✓
B.Debugging
C.Test and defect management
D.Risk analysis

Resposta Correta

A: Configuration management

Explicação

A is correct. Configuration management is missing if the code is not being properly versioned and tracked.

Praticar Este ConjuntoVer Todas as Questões

Mais Questões desta Prova

#1

When the tester verifies the test basis while designing tests early in the lifecycle, which test objective is being achieved?

#2

In some Agile teams, people are encouraged to use their skills to help the team, regardless of their role. This could mean that testers help the developers write code and developers help testers test. What is this approach called?

#3

Which of the following is a correct statement?

#4

Why is it important to avoid the principle of tests wearing out?

#5

When following a standard test process, when should the test control activity take place?