Questão 271ISTQB CTFL v4.0 Sample Exam A

You are testing a mobile application that allows users to find a nearby restaurant based on the type of food they want to eat. Consider the following list of test cases, priorities (i.e., a smaller number means a higher priority), and dependencies: Test case Logical Test condition covered Priority number dependency TC 001 Select type of food 3 none TC 002 Select restaurant 2 TC 001 TC 003 Get direction 1 TC 002 TC 004 Call restaurant 2 TC 002 TC 005 Make reservation 3 TC 002 Which of the following test cases should be executed as the third one?

Test case numberTest condition coveredPriorityLogical dependency
TC 001Select type of food3none
TC 002Select restaurant2TC 001
TC 003Get direction1TC 002
TC 004Call restaurant2TC 002
TC 005Make reservation3TC 002

Opções de Resposta

A.TC 003✓
B.TC 005
C.TC 002
D.TC 001

Resposta Correta

A: TC 003

Praticar Este ConjuntoVer Todas as Questões

Mais Questões desta Prova

#239

Which of the following statements describe a valid test objective?

#240

Which of the following options shows an example of test activities that contribute to success?

#241

You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

#242

You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality. Which of the following activities is a part of test analysis?

#243

Which of the following factors (i-v) have SIGNIFICANT influence on the test process? i. The SDLC ii. The number of defects detected in previous projects iii. The identified product risks iv. New regulatory requirements forcing formal white-box testing v. The test environment setup