Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made:  Most optimistic estimation: 2 person-hours  Most likely estimation: 11 person-hours  Most pessimistic estimation: 14 person-hours What is the final estimate?

Test case numberTest condition coveredPriorityLogical dependency
TC 001Select type of food3none
TC 002Select restaurant2TC 001
TC 003Get direction1TC 002
TC 004Call restaurant2TC 002
TC 005Make reservation3TC 002

Opções de Resposta

A.9 person-hours
B.14 person-hours
C.11 person-hours
D.10 person-hours

Resposta Correta

D: 10 person-hours