As a test manager you are responsible for testing the following requirements: R1 - Process anomalies R2 - Synchronization R3 - Approval R4 - Problem solving R5 - Financial data R6 - Diagram data R7 - Changes to the user profile Notation: Logical requirement dependencies (A -> B means, that B depends on A): R3 R4 R1 R2 R5 R6 R7 Which one of the following options structures the test execution schedule according to the requirement dependencies? R5 R6

Opções de Resposta

A.R1 -> R3 -> R4 -> R7 -> R2 -> R5 -> R6 .
B.R1 -> R3 -> R2 -> R4 -> R7 -> R5 -> R6.
C.R1 -> R3 -> R2 -> R5 -> R6 -> R4 -> R7.
D.R1 -> R2 -> R5 -> R6 -> R3 -> R4 -> R7.

Resposta Correta

C: R1 -> R3 -> R2 -> R5 -> R6 -> R4 -> R7.