You have received the following description section in a defect report: The report executed per the attached steps, but the data was incorrect. For example, the information in column 1 was wrong. See the attached screenshot. This report is critical to the users and they will be unable to do their jobs without this information. What is the biggest problem with this defect report?
| Test Case ID | Duration | Risk Priority | Dependency |
|---|---|---|---|
| 1 | 30 mins | Low | 6 |
| 2 | 10 mins | Medium | none |
| 3 | 45 mins | High | 1 |
| 4 | 30 mins | High | 2 |
| 5 | 10 mins | Medium | 4 |
| 6 | 15 mins | Low | 2 |
選択肢
A.The developer won’t know how important the problem is
B.The developer won’t know how to repeat the test
C.The developer won’t be able to see what the tester is saying is wrong
D.The developer won’t know what the tester expected to see✓
正解
D: The developer won’t know what the tester expected to see