問題 76Foundation 2018 Sample Exam 1

You have received the following description section in a defect report: The report executed per the attached steps, but the data was incorrect. For example, the information in column 1 was wrong. See the attached screenshot. This report is critical to the users and they will be unable to do their jobs without this information. What is the biggest problem with this defect report?

Test Case IDDurationRisk PriorityDependency
130 minsLow6
210 minsMediumnone
345 minsHigh1
430 minsHigh2
510 minsMedium4
615 minsLow2

選択肢

A.The developer won’t know how important the problem is
B.The developer won’t know how to repeat the test
C.The developer won’t be able to see what the tester is saying is wrong
D.The developer won’t know what the tester expected to see✓

正解

D: The developer won’t know what the tester expected to see

この試験セットで練習するすべての問題を見る

この試験の他の問題

#40

What is the test basis?

#41

When the tester verifies the test basis while designing tests early in the lifecycle, which common test objective is being achieved?

#42

When following the fundamental test process, when should the test control activity take place?

#43

Which of the following is a correct statement?

#44

Which of the following is an example of debugging?