問題 335ISTQB CTFL v4.0 Sample Exam B

You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data. Project Development effort Test effort ($) ($) P1 800,000 40,000 P2 1,200,000 130,000 P3 600,000 70,000 P4 1,000,000 120,000 The estimated development effort for the new project is $800,000. What is your estimate of the test effort in this project?

ProjectDevelopment effortTest effort
($)($)
P1800,000 40,000
P21,200,000 130,000
P3600,000 70,000
P41,000,000 120,000

選択肢

A.$40,000
B.$80,000✓
C.$81,250
D.$82,500

正解

B: $80,000

この試験セットで練習するすべての問題を見る

この試験の他の問題

#305

Which of the following is an example of why testing is necessary?

#306

Which of the following statements about quality assurance (QA) and/or quality control (QC) is correct?

#307

One of the ‘principles of testing’ states that exhaustive testing is impossible. Which of the following is an example of addressing this principle in practice?

#308

Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?

#309

Which of the following is MOST likely to impact how testing is performed for a given test object?