ISTQB Quiz
nav.blog試験セット問題練習クイズ
ENVIDEPTJA
ENVIDEPTJA

ISTQB Quiz

ISTQB Foundation Level 無料練習テスト

(c) 2026 ISTQB Quiz - Not affiliated with ISTQB

ホーム/問題/#300
問題 300ISTQB CTFL v4.0 Sample Exam A

During risk analysis the team considered the following risk: “The system allows too high a discount for a customer”. The team estimated the risk impact to be very high. What can one say about the risk likelihood?

選択肢

A.It is also very high. High risk impact always implies high risk likelihood
B.It is very low. High risk impact always implies low risk likelihood
C.One cannot say anything about risk likelihood. Risk impact and risk likelihood are independent.✓
D.Risk likelihood is not important with such a high-risk impact. One does not need to define it.

正解

C: One cannot say anything about risk likelihood. Risk impact and risk likelihood are independent.

この試験セットで練習するすべての問題を見る

この試験の他の問題

#239

Which of the following statements describe a valid test objective?

#240

Which of the following options shows an example of test activities that contribute to success?

#241

You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

#242

You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality. Which of the following activities is a part of test analysis?

#243

Which of the following factors (i-v) have SIGNIFICANT influence on the test process? i. The SDLC ii. The number of defects detected in previous projects iii. The identified product risks iv. New regulatory requirements forcing formal white-box testing v. The test environment setup