問題 276ISTQB CTFL v4.0 Sample Exam A

You received the following defect report from the developers stating that the anomaly described in this test report is not reproducible. Application hangs up 2022-May-03 – John Doe – Rejected The application hangs up after entering “Test input: $ä” in the Name field on the new user creation screen. Tried to log off, log in with test_admin01 account, same issue. Tried with other test admin accounts, same issue. No error message received; log (see attached) contains fatal error notification. Based on the test case TC-1305, the application should accept the provided input and create the user. Please fix with high priority, this feature is related to REQ-0012, which is a critical new business requirement. What critical information is MISSING from this test report that would have been useful for the developers?

選択肢

A.Expected result and actual result
B.References and defect status
C.Test environment and test item✓
D.Priority and severity

正解

C: Test environment and test item

この試験セットで練習するすべての問題を見る

この試験の他の問題

#239

Which of the following statements describe a valid test objective?

#240

Which of the following options shows an example of test activities that contribute to success?

#241

You have been assigned as a tester to a team producing a new system incrementally. You have noticed that no changes have been made to the existing regression test cases for several iterations and no new regression defects were identified. Your manager is happy, but you are not. Which testing principle explains your skepticism?

#242

You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality. Which of the following activities is a part of test analysis?

#243

Which of the following factors (i-v) have SIGNIFICANT influence on the test process? i. The SDLC ii. The number of defects detected in previous projects iii. The identified product risks iv. New regulatory requirements forcing formal white-box testing v. The test environment setup