Which activities are carried out within the planning of a formal review?

選択肢

A.Collection of metrics for the evaluation of the effectiveness of the review.
B.Answer any questions the participants may have.
C.Verification of input criteria for the review..
D.Evaluation of the review findings against the exit criteria.

正解

C: Verification of input criteria for the review..