問題 114Foundation 2018 Sample Exam 2

You are getting ready to test another upgrade of an ERP system. The previous upgrade was tested by your team and has been in production for several years. For this situation, which of the following is the most appropriate test effort estimation technique?

Test IDNameDependencyPriority
1Purchase Itemnone2
2Receive InvoiceTest 13
3Receive GoodsTest 12
4Send PaymentTest 23
5Report PaymentsTest 41

選択肢

A.Effort-based
B.Expert-based
C.Metric-based✓
D.Schedule-based

正解

C: Metric-based

この試験セットで練習するすべての問題を見る

この試験の他の問題

#80

Which of the following is the activity that removes the cause of a failure?

#81

As a tester, which of the following is a key to effectively communicating and maintaining positive relationships with developers when there is disagreement over the prioritization of a defect?

#82

Why is software testing sometimes required for legal reasons?

#83

In what way does root cause analysis contribute to process improvement?

#84

Why is it important to avoid the pesticide paradox?