Which of the following is a project risk?

Antwortmöglichkeiten

A.A module that performs incorrect calculations due to a defect in a formula
B.A failed performance test
C.An issue with the interface between the system under test and a peripheral device
D.A problem with the development manager which is resulting in his rejecting all defect reports

Richtige Antwort

:

Weitere Fragen aus dieser Prüfung