Which of the following is an example of how product risk analysis influences thoroughness and scope of testing?

Antwortmöglichkeiten

A.The test manager monitors and reports the level of all known risks on a daily basis so the stakeholders can make an informed decision on the release date
B.One of the identified risks was "Lack of support of open-source databases", so the team decided to integrate the system with an open-source database
C.During the quantitative risk analysis, the team estimated the total level of all identified risks and reported it as the total residual risk before testing
D.Risk assessment revealed a very high level of performance risks, so it was decided to perform detailed performance efficiency testing early in the SDLC

Richtige Antwort

D: Risk assessment revealed a very high level of performance risks, so it was decided to perform detailed performance efficiency testing early in the SDLC